Hi,
you can set up the production integration scenarion with EWM with different organizational models
- you use just one storage location (from where the material is staged and from where the GI is posted when production consumes the material)
- two storage locations
- Option a: both are using the same warehouse number
- Option b: one is using EWM, the other has not warehouse management at all
- Option c: both use separate EWM controled warehouse numbers.
In the first two possibilities (only one sloc or both using the same whn) you use storage type 1000.
As I understand the scenario, for the other options, where the GI is posted from the warehouse to post the GR in the storage location for the production (where later the consumption is posted) you use 1005. This has also the role K, so it is not a staging area per se. But I have never set up the scenario like this.
Brgds
Juergen
Here are the scenarios described: Organizational Model for Production Supply - Goods Issue - SAP Library
Message was edited by: Juergen Pitz