Yes Juergen , the problem is exactly there. But I am not sure how do I create Putaway WT at a later stage ..... My POSC is standard :
Unloading
Packing
Putaway
as per the steps assigned in POSC ...
The tasks are created in sequence , but first two warehouse tasks are created simulataneously ( for Unloading -open WT and putaway - in waiting -B). How do I shift creation of Putaway warehouse task at a later stage ? Putaway WT is anyways 3rd in sequence ...and Auto flag is not selected for that.
Is it controlled by sequence .....below in table ...
Assignment of the storage process steps to the storage process:
Sequence No. | Step | Auto | Prod/HU WT | Duration |
1 | ZB01-unload | Selected | Deselected | 5 |
2 | IPK1-Pack | Selected | Selected | 20 |
3 | IPT1-Putaway | Deselected | Deselected | 30 |
it looks sequence no. needs to be changed ....I will try by changing sequence and check.
Thanks for exactly pointing out what is going wrong.
Regards / Vinod Sedani